Equipment qualification for the introduction of a new production line: Tips and tricks

In every project, there are challenges and unforeseen situations that need to be overcome. This is no different in an equipment qualification project for the introduction of a new production line. This blog shares some tips and tricks that can be used in future equipment qualification projects.

Contact us

Fill out the form and we will contact you shortly.

Naam
Privacy Policy 
Continue reading

What is equipment qualification?

Equipment qualification is a series of inspections, tests, and assessments to ensure that a given piece of equipment is compliant and ensures reliable performance. It is required to prove that a given piece of equipment does, on a consistent basis, what it is supposed to do. In the pharmaceutical industry, equipment qualification is critical because the slightest error or misuse can pose a costly risk and time delay for the pharmaceutical product owner and their manufacturer.

Planning

Good planning is one of the most important building blocks to make a validation project successful. This sounds very logical, but in reality it is not obvious.

To speak of good planning, several factors need to be taken into account. A first factor is a feasible schedule for all teams involved. Each team, for its own tasks, will draw up its own schedule. All the schedules of all the teams should be laid alongside each other to create one overall schedule. A deadline may be feasible for a particular team but the same deadline may not be feasible in the overall planning. Is no overall planning set up? Then, sooner or later, deadlines will overlap and cannot be met.

Taking into account possible project delays, is a second important factor to consider. Experience has shown that no project runs flawlessly and perfectly. So allow enough margin for deadlines to avoid missing deadlines time after time. Even if possible project delays are already taken into account, challenges will still arise during an equipment qualification project that will prevent certain deadlines from being met. At such times, adjusting the planning is unavoidable. Postponing deadlines is strongly advised against. Although it may seem like the easiest solution, especially at the beginning of a project when the date for final delivery of the new production line is still far in the future. Postponing deadlines usually has an impact on subsequent deadlines. A better way to deal with such a situation is to see if certain tasks can be swapped. For this, teamwork and good communication between the different teams is very important.

Teamwork and communication

A project stands or falls with good teamwork and communication. The team of which you yourself are part, needs to communicate well about who will take care of which system or task. A daily follow-up meeting is an efficient way to follow up on statuses of systems or tasks, distribute new systems or tasks, and discuss issues that are struggling.

Furthermore, there is a need for teamwork and communication between the different teams. Qualification of equipment always involves several parties e.g. a validation team, a calibration team, IT, a system owner, QA, a sampling, team engineering… It is not the case that the same teams are involved for every system. So it is important to check which teams are involved for each system. Then, when there is a problem with that system, a meeting can be set up with just the teams involved.

During a weekly follow-up meeting with all teams, the status of the systems can be monitored, delays can be discussed and the impact of those delays on the other teams can be determined. To make a follow-up meeting, with all teams, run efficiently, it is a good idea to appoint someone within each team to monitor the weekly follow-up meeting. This way, you keep the number of people in the meeting to a minimum.

Moreover, a person or team should be appointed to be the general point of contact for everything related to the project. This team is also responsible for following up the planning and adjusting it in time. The weekly follow-up meeting is usually led by someone from this team.

Design Qualification

The introduction of a new production line, involves the purchase of many different systems. A potential pitfall is that certain brands or types of systems are purchased because they already exist on site and work well. But for each production line, systems have different specifications they have to meet. It is therefore very important to check whether all systems meet the predefined specifications to be suitable for the intended purpose, meeting regulatory and process needs.

Conclusie

With feasible planning, good teamwork, clear communication and comprehensive design qualification, an equipment qualification project can be carried out successfully. Do pitfalls or challenges come up during the project? Don’t see it as a setback but as a learning opportunity for future projects.

Your partner in quality, safety, and compliance

The life sciences sector requires specialized knowledge and reliable support. With our broad expertise, we help organizations comply with laws and regulations, ensure quality, and continue to innovate with confidence.

Related services

Medical Team Performing Surgical Operation in Bright Modern Operating Room

Quality Management System (QMS)

Program and Project Management

Related Articles

10 Jul 2026

Project Management

In the complex and highly regulated world of the pharmaceutical industry, project management plays a pivotal role to bring life-saving medications and treatments to the market. From drug discovery to clinical trials and regulatory approval, effective project management is essential for managing timelines, resources, and compliance. Let’s dive in some practical tips and tricks specifically for navigating the complexities of project management in the pharmaceutical sector.

10 Jul 2026

Implementation of the European Clinical Trial Regulation (EU-CTR)

By the end of this month (31st of January 2025), the final deadline is reached in the transition period for the implementation of the European Clinical Trial Regulation (EU-CTR). What is it and what is the difference with the previous European Clinical Trial Directive (EU-CTD)?

10 Jul 2026

Radiopharmaceutical & Selective Internal Radiation Treatments: Overcoming Challenges and Embracing Future Opportunities

Radiopharmaceutical and selective internal radiation treatments have emerged as a transformative force in the pharmaceutical industry, offering precision, personalized therapies for patients with conditions such as cancer and other serious diseases.

10 Jul 2026

Potential Pitfalls in an MES Project

Just as every project has its pitfalls, the same is true for a Manufacturing Execution System (MES) implementation project. Implementing electronic batch records is no easy task. That’s why, in the blog below, we’ll share a few pitfalls so you can prepare for a successful implementation within your company.

10 Jul 2026

To-Do List for Successful Preparation for ISO 13485:2016 Certification

A few weeks ago, Sofie and Abbie introduced the pillars of the ISO 13485:2016 standard and explained why an organization benefits from having its quality management system (QMS) certified. Convinced of the benefits of investing in an ISO 13485:2016 certificate, we’d like to share how you can properly prepare for the certification audit.

10 Jul 2026

Streamlining Post-Marketing Surveillance with IMDRF Coding

Since the implementation of the Medical Device Regulation (MDR) in Europe, companies have had to maintain and execute a post-marketing surveillance (PMS) procedure. This systematic process involves collecting and analysing data on the performance and safety of medical devices after they have been released to the market. The primary goal is to help manufacturers identify and address potential issues that may arise during actual use, monitor the market for known risks, and identify new risks.

10 Jul 2026

ISO 9001:2015 in Life Sciences Industry

In the life sciences industry, maintaining high quality standards is critical not only to the success and sustainability of organizations but also to patient safety and compliance. ISO 9001:2015, part of the ISO 9000 family, provides a robust framework for quality management systems (QMS) that can be used in organizations in the life sciences, including pharmaceutical, natural technology, including medical devices. This article examines the key features of ISO 9001:2015, its benefits, implementation methods, potential pitfalls, and impact in the life sciences.